A8 Motorway – stay cable bridge over river Odra

WrocLaw, Poland, 2011 | construction methods | on-site

Say cable bridge:

  • 2 x 256 m main span.
  • Deck was incrementally launched in the same time as pylon was being erected to reduce construction time.
  • Both independent decks suspended to a single pylon.
  • Deck was launched from the same casting yard as one of the approach overpasses.